- Customer
- Ekibastuz GRES-1 LLP
- Sibtechenergo OJSC
- Ekibastuz-energoremont LLP
- Karaganda BI Energy Plus LLP
- Kazakhmys Corporation LLP
- TekhProject LLP
- Promyshlennaya Gazoochistka Kazakhstana LLP
- Eurasian Energy Corporation JSC
- Karaganda BI Energy LLP
- KAZPROMPRIBOR LLP
- Alga A JSC
- Kazenergonaladka Firm LLP
- Aktobe HPP JSC
- Sary-Arka Spetskoks LLP
- SPACE-MOTOR CJSC
- AES Ust-Kamenogorsk HPP LLP
- STROYINDUSTRIYA LLP
- AES Shulba Hydroelectric Power Station LLP
- Nur Stroy Pavlodar LLP
- Firma Partner Plus LLP
- Energo Spets Stroy LLP
- Aluminum of Kazakhstan JSC
- Nitro Sibir Kazakhstan LLP
- KazTransCom JSC
- Shubarkol Komir JSC
- KAZ Minerals Bozshakol LLP
- SEVKAZENERGOPROM RESEARCH AND PRODUCTION COMPANY LLP
- Kazzinc LLP
- TNC Kazchrome JSC
- Kazpromcontrol LLP
- Pavlodar-Soda LLP
- Energometroservice LLP
- Altyn Group LLP
- TechnoGroupService LLP
- EKRA KAZAKHSTAN LLP
- Kazakhstan Aluminium Smelter JSC
- Atyrau Oil Refinery LLP
- Ust-Kamenogorsk TPP LLP
№ | Name | The objects | Type of project | Year | Note |
26 |
Development of a working project: “Reconstruction of warehouse No. 1202 fuels and lubricants-2 of the Vostochnyi open-pit mine of EEC JSC |
PP of Eurasian Energy Corporation JSC |
Technological project |
2018-2019 |
The positive conclusion of the Gosexpertiza RSE was received |
27 |
Development of an external power supply scheme for a consumer of Pavlodar-Soda LLP |
Pavlodar-Soda LLP |
Pre-project work |
2018 |
|
28 |
Development of the working project of Aluminum of Kazakhstan JSC, Pavlodar Aluminum Plant. TPP-1, Pavlodar. Replacement of car dumper VRS-90 No. 2” |
TPP of Aluminum of Kazakhstan JSC |
Technological project |
2018 |
Received a positive conclusion from a comprehensive non-departmental examination. |
29 |
Implementation of a working draft on the topic: “Aluminum of Kazakhstan Pavlodar JSC, Pavlodar Aluminum Plant, TPP. Replacement of the main steam pipe k/a. No. 6” |
TPP of Aluminum of Kazakhstan JSC |
Technological project |
2018 |
Received a positive conclusion from a comprehensive non-departmental examination. |
30 |
Implementation of the project for the reconstruction of the eastern part of the ring in high-voltage electric transmission lines -6 kV, quarry of KAZ Minerals Bozshakol LLP |
KAZ Minerals Bozshakol LLP |
Energy project |
2018 |
Received a positive conclusion from a comprehensive non-departmental examination. The facility was commissioned according to the project. |