- The Project
- Ekibastuz GRES-1
- KEGOC JSC
- Vostochnyi open-pit mine Eurasian Energy Corporation JSC
- ES JSC "Eurasian Energy Corporation"
- Zhezkazgan TPP, Kazakhmys Corporation LLP
- Ekibastuz GRES-2 Station JSC
- Alga A JSC
- Aktobe Ferroalloy Plant – branch of JSC "TNK "Kazchrome"
- Kazakhmys Smelting LLP
- Shubarkol Komir JSC
- Ust-Kamenogorsk CHPP
- Karaganda BI Energy Plus LLP
- Shulbinskaya HPP
- Aksu Ferroalloy Plant – branch of Transnational company Kazchrome JSC
- Prommashkomplekt LLP
- Kazakhmys Energy LLP
- Energo Spets Stroy LLP
- Aluminum of Kazakhstan JSC
- Nitro Sibir Kazakhstan LLP
- KazTransCom JSC
- Don Ore-Dressing Plant - branch of TNC Kazchrome JSC
- KAZ Minerals Bozshakol LLP
- Bukhtarma Hydropower Complex
- Pavlodar-Soda LLP
- Atyrau Oil Refinery LLP
- Altyn Group LLP
- TechnoGroupService LLP
- PP Solutions LLP
- Kaz Green Energy LLP
- Ekibastuzteploenergo LLP
- Pavlodar-Soda LLP
- Keregetas mine of Aluminum of Kazakhstan JSC
- STEC-3 3-Energoortalyk JSC
- Zhezkazgan Plant of Metal Structures LLP
- Bogatyr Komir LLP
- KSP Steel LLP
- Copper Company Konrad LLP
- Technogruppservice LLP
- Shymkent Thermal Power Plant-3 JSC 3-Energoortalyk
№ | Name | Customer | Type of project | Year | Note |
126 |
Development of a project on the topic: "Reconstruction of raw water pipelines", Bulat Nurzhanov Ekibastuz GRES-1 LLP |
STROYINDUSTRIYA LLP |
Technological project |
2015 |
The positive conclusion of the Gosexpertiza RSE was received |
127 |
Building of the heat treatment furnace, the checkpoint building and the open warehouse of the plant for the manufacture of heating surfaces and metal structures |
Energo Spets Stroy LLP |
Technological project |
2015 |
The facility was commissioned according to the project. |
128 |
Reconstruction of the suction unit of crushing unit No. 3 of workshop No. 6 |
Kazenergonaladka Firm LLP |
Technological project |
2015-2016 |
The positive conclusion of the Gosexpertiza RSE was received. |
129 |
Development of the feasibility study "Construction of the second input of the fuel supply path in the power plant of EEC JSC |
Kazenergonaladka Firm LLP |
Pre-project work |
2015 |
|
130 |
Reconstruction of relay protection devices for 110 kV lines No. 141,142,143,144 at the TPP of Aluminum of Kazakhstan JSC in Pavlodar Substation |
Kazenergonaladka Firm LLP |
Energy project |
2015-2016 |
The positive conclusion of the Gosexpertiza RSE was received. The facility was commissioned according to the project. |