- The Project
- Ekibastuz GRES-1
- KEGOC JSC
- Vostochnyi open-pit mine Eurasian Energy Corporation JSC
- ES JSC "Eurasian Energy Corporation"
- Zhezkazgan TPP, Kazakhmys Corporation LLP
- Ekibastuz GRES-2 Station JSC
- Alga A JSC
- Aktobe Ferroalloy Plant – branch of JSC "TNK "Kazchrome"
- Kazakhmys Smelting LLP
- Shubarkol Komir JSC
- Ust-Kamenogorsk CHPP
- Karaganda BI Energy Plus LLP
- Shulbinskaya HPP
- Aksu Ferroalloy Plant – branch of Transnational company Kazchrome JSC
- Prommashkomplekt LLP
- Kazakhmys Energy LLP
- Energo Spets Stroy LLP
- Aluminum of Kazakhstan JSC
- Nitro Sibir Kazakhstan LLP
- KazTransCom JSC
- Don Ore-Dressing Plant - branch of TNC Kazchrome JSC
- KAZ Minerals Bozshakol LLP
- Bukhtarma Hydropower Complex
- Pavlodar-Soda LLP
- Atyrau Oil Refinery LLP
- Altyn Group LLP
- TechnoGroupService LLP
- PP Solutions LLP
- Kaz Green Energy LLP
- Ekibastuzteploenergo LLP
- Pavlodar-Soda LLP
- Keregetas mine of Aluminum of Kazakhstan JSC
- STEC-3 3-Energoortalyk JSC
- Zhezkazgan Plant of Metal Structures LLP
- Bogatyr Komir LLP
- KSP Steel LLP
- Copper Company Konrad LLP
- Technogruppservice LLP
- Shymkent Thermal Power Plant-3 JSC 3-Energoortalyk
№ | Name | Customer | Type of project | Year | Note |
181 |
Management, control of fuel oil rate in oil and fuel oil equipment, Ekibastuz GRES-1 |
Karaganda BI Energy LLP |
Energy project |
2011-2012 |
|
182 |
Development of design and estimate documentation Replacement of an ATTTsTG-120000 type 1AT communication autotransformer with an ATDTsTN-125000 autotransformer of the Zhezkazgan TPP |
Kazakhmys Corporation LLP |
Energy project |
2011 |
The facility was commissioned according to the project |
183 |
Automated process control system for a 500 MW unit No. 1, 2 at Ekibastuz GRES-2 Station JSC |
KAZPROMPRIBOR LLP |
Energy project |
2011-2012 |
The positive conclusion of the Gosexpertiza RSE was received. Industrial-control system of power unit st. No. 1 was commissioned according to the project. |
184 |
Development of design and estimate documentation “Designing of service sites for KET-20” at Bulat Nurzhanov Ekibastuz GRES-1 LLP |
Karaganda BI Energy LLP |
Architectural and construction project |
2011-2012 |
The facility was commissioned according to the project |
185 |
Development of design and estimate documentation “Replacement of an ATTTsTG-120000 type 1AT communication autotransformer with an ATDTsTN-125000 autotransformer of the Zhezkazgan TPP, Kazakhmys Corporation LLP |
Kazakhmys Corporation LLP |
Energy project |
2011 |
The facility was commissioned according to the project. |