- The Project
- Ekibastuz GRES-1
- KEGOC JSC
- Vostochnyi open-pit mine Eurasian Energy Corporation JSC
- ES JSC "Eurasian Energy Corporation"
- Zhezkazgan TPP, Kazakhmys Corporation LLP
- Ekibastuz GRES-2 Station JSC
- Alga A JSC
- Aktobe Ferroalloy Plant – branch of JSC "TNK "Kazchrome"
- Kazakhmys Smelting LLP
- Shubarkol Komir JSC
- Ust-Kamenogorsk CHPP
- Karaganda BI Energy Plus LLP
- Shulbinskaya HPP
- Aksu Ferroalloy Plant – branch of Transnational company Kazchrome JSC
- Prommashkomplekt LLP
- Kazakhmys Energy LLP
- Energo Spets Stroy LLP
- Aluminum of Kazakhstan JSC
- Nitro Sibir Kazakhstan LLP
- KazTransCom JSC
- Don Ore-Dressing Plant - branch of TNC Kazchrome JSC
- KAZ Minerals Bozshakol LLP
- Bukhtarma Hydropower Complex
- Pavlodar-Soda LLP
- Atyrau Oil Refinery LLP
- Altyn Group LLP
- TechnoGroupService LLP
- PP Solutions LLP
- Kaz Green Energy LLP
- Ekibastuzteploenergo LLP
- Pavlodar-Soda LLP
- Keregetas mine of Aluminum of Kazakhstan JSC
- STEC-3 3-Energoortalyk JSC
- Zhezkazgan Plant of Metal Structures LLP
- Bogatyr Komir LLP
- KSP Steel LLP
- Copper Company Konrad LLP
- Technogruppservice LLP
- Shymkent Thermal Power Plant-3 JSC 3-Energoortalyk
№ | Name | Customer | Type of project | Year | Note |
186 |
Development of design and estimate documentation “Modernization of electrical equipment for fuel supply, oil-fuel oil facilities, rotary loading machines” at Bulat Nurzhanov Ekibastuz GRES-1 |
Karaganda BI Energy LLP |
Energy project |
2011-2012 |
|
187 |
Development of design and estimate documentation “Replacement of sections VR-04-10; sections 33-34 NO; sections BNS-1,2; sections 31-32 NO; sections 5-6 NO; sections 75-76 NO; sections 77-78 |
Karaganda BI Energy LLP |
Energy project |
2011-2012 |
The facility was commissioned according to the project. |
188 |
Replacement of the working thyristor excitation system of power unit st.7 |
Sibtechenergo OJSC |
Energy project |
2010 |
The facility was commissioned according to the project |
189 |
Reconstruction of the emergency control complex of the Astana energy center |
TekhProject LLP |
Energy project |
2010 |
The positive conclusion of the Gosexpertiza RSE was received. The facility was commissioned according to the project |
190 |
Design work on the reconstruction of fuel supply of stage 2 |
Ekibastuz-energoremont LLP |
Energy project |
2010-2011 |
The positive conclusion of the Gosexpertiza RSE was received. The facility was commissioned according to the project |